ANOTHER STAGE OF WORKS NEAR COMPLETION

Works involving a wide range of activities are progressing at the Museum of Independence in Warsaw. They cover the entire interior of the building, from the basement to the attic and its area, which is why we carry out them in stages. Currently we are carrying out interior finishing works. In previous news we wrote about earlier stages of works on this object – read about here >>.

We have started laying stone floors and stair steps, and on the first floor we have carried out the renovation of parquets. The historic doors, which we have renovated, are almost finished and will soon be inserted, in addition, new stylized doors will be installed at the end of the month with glazed aluminum walls. We also inserted steel and aluminum doors in the required places.
The attic works are also coming to an end. We have completed the stage of thermal insulation with wool and the construction of the arched ceiling formwork. At the same time, we have started to finalize the building of partition walls in the attic.

In the next stages, we will carry out the renovation of the facade with the replacement of window joinery, roofing and replacement of gutter and downpipes. We will also redevelop the area around the palace and we will perform the installation of the illumination of its facade.

The completion of works is expected at the end of June 2019.